凤来大溪河特大桥拱脚腹杆钢-混连接段构造设计
基金项目(Foundation): 中铁二院科技开发司控项目(KSNQ224025)
邮箱(Email): 767749377@qq.com
DOI:
发布时间: 2026-04-10
出版时间: 2026-04-10
网络发布时间: 2026-04-10
移动端阅读
摘要:

凤来大溪河特大桥拱脚腹杆钢-混连接段采用了一种新型完全承压式锚固构造,该构造将承受巨大荷载的拱脚腹杆内力传递到混凝土拱座基础,同时起到刚度过渡的作用,其上部借鉴钢桁架节点板形式,与下部的承压板格构体系相结合,主要由拼接板、预应力高强螺纹钢筋、承压板、开孔板等构件组成。不同于传统拱桥采用先铰接后固结的施工方法,该构造在施工完首节段钢桁架就可通过张拉高强螺纹钢筋完成与拱座基础的固结,减少了封铰步骤及高空作业的风险。本文详细介绍了拱脚腹杆钢-混连接段的静力计算内容,通过建立此构造局部精细化计算模型,研究在控制荷载作用下锚固构造的应力分布规律,计算结果表明:此种完全承压式锚固构造受力明确,各项指标均满足设计要求。

Abstract:

The steel-concrete connection section of the arch foot web member of the Fenglai Daxi River Extra-large Bridge adopts a novel fully load-bearing anchoring structure. This structure not only transfers the internal forces of the arch foot web member, which bear significant loads, to the concrete abutment foundation but also serves as a stiffness transition. Its upper part adopts a steel truss node plate form, combined with the lower load-bearing plate lattice system. It primarily consists of splicing plates, prestressed high-strength threaded steel bars, load-bearing plates, perforated plates, and other components. Unlike the traditional construction method of arch bridges, which involves hinging first and then consolidation, this structure can complete the consolidation with the abutment foundation by tensioning the high-strength threaded steel bars after the first section of the steel truss is constructed, reducing the number of hinge sealing steps and the risks associated with high-altitude operations. This article provides a detailed introduction to the static calculation content of the steel-concrete connection section of the arch foot web member. By establishing a local refined calculation model for this structure, the stress distribution law of the anchoring structure under controlled loads is studied. The calculation results show that this fully load-bearing anchoring structure has clear stress distribution and meets all design requirements.

参考文献

[1]顾安邦,向中富.桥梁工程[M].北京:人民交通出版社,2011.

[2]李勇.大跨度钢-混凝土组合桥梁理论与应用[M].北京:科学出版社,2014.

[3]ROVNAK M,DURICOVA A.Behaviour Evaluation of Shear-Connection by Means of Shear Connection Strips[J].Steel&Composite Structures,2004,4(3):247-263.

[4]ROVNAK M,DURICOVA A,IVANCO V.Non-Traditional Shear Connections in Steel-Concrete Composite Structures[J].Composite and Hybrid Structures,2000,1(2):305-312.

[5]杨清华,柴生波,王秀兰,等.大跨度钢箱系杆拱桥主拱钢-混连接段受力分析[J].公路工程,2023,48(4):31-36,51.

[6]郑尚敏,程海根,冯龙,等.大跨度系杆拱桥主拱钢-混凝土连接段受力状态分析[J].铁道建筑,2020,60(3):9-12.

[7]魏奇芬,叶文海.香溪长江公路大桥主拱钢-混结合部设计与计算[J].现代交通技术,2017,14(5):30-33.

[8]彭帆,巢万里.刚架系杆拱桥钢-混凝土接头传力行为研究[J].公路工程,2011,36(2):72-75,136.

[9]JTG D60—2015 公路桥涵设计通用规范[S].

[10]JTG D64—2015 公路钢结构桥梁设计规范[S].

[11]GB 50917—2013 钢-混凝土组合桥梁设计规范[S].

[12]耿波,王芳,宋军,等.青衣江大桥钢混连接段局部应力分析[J].公路交通技术,2011(6):49-53.

[13]JTG 3362—2018 公路钢筋混凝土与预应力混凝土桥梁结构设计规范[S].

[14]JTG 3363—2019 公路桥涵地基与基础设计规范[S].

[15]JTG/TD 65-05—2015 公路悬索桥设计规范[S].

基本信息:

中图分类号:U442.5

引用信息:

[1]张扬,李松涛,汪洋,等.凤来大溪河特大桥拱脚腹杆钢-混连接段构造设计[J].铁道建筑().

基金信息:

中铁二院科技开发司控项目(KSNQ224025)

发布时间:

2026-04-10

出版时间:

2026-04-10

网络发布时间:

2026-04-10