大纵坡长悬臂钢箱梁斜拉扣挂转体关键技术
基金项目(Foundation): 中铁十一局集团A类科技创新项目(24-AⅡ-03)
邮箱(Email):
DOI:
发布时间: 2026-07-13
出版时间: 2026-07-13
网络发布时间: 2026-07-13
移动端阅读
摘要:

针对铁路交叉工程长悬臂、大纵坡T构钢箱梁转体施工存在变形大、风险高、控制难等问题,提出并应用多点斜拉扣挂辅助转体关键技术。研发模块化临时扣塔与多索面斜拉体系分散主梁受力,将100m悬臂梁端下挠控制在25cm以内;采用斜拉索智能均匀张拉技术,使单束27根钢绞线索力离散误差小于±2%;攻克大纵坡T构墩顶转体控制与高位落梁技术,确保受限空间内精确转体与体系转换;搭建BIM与无线传感融合数字化监控平台,完成转体实时监测与智能预警。工程实践表明,桥梁转体就位后轴线与高程偏差仅5 mm,精度控制达毫米级。该技术显著提升了施工安全性与经济性,为同类跨铁路、公路桥梁工程提供理论支撑与技术参考。

Abstract:

In view of large deformation, high construction risk and difficult control in the swivel construction of long-cantilever T-frame steel box girders with large longitudinal slopes for railway crossing projects, the key technology of multi-point stay-cable fastening assisted swivel was proposed and applied. A modular temporary buckle pylon and multi-cable-plane stay cable system were developed to disperse the main girder load, controlling the deflection at the end of the 100 m cantilever within 25 cm. Intelligent uniform tensioning technology for stay cables was adopted, restricting the cable force deviation of a single bundle of 27 steel strands to less than ±2%. The pier-top swivel control and high-level girder landing technologies for large-longitudinal-slope T-frames were overcome to ensure accurate swivel and system conversion in restricted spaces. A digital monitoring platform integrating BIM and wireless sensing was constructed to realize real-time monitoring and intelligent early warning during the entire swivel process.Engineering practice shows that the axis and elevation deviations of the bridge after swivel positioning are only 5 mm, demonstrating millimeter-level precision. This technology significantly improves construction safety and economic efficiency, and provides theoretical support and technical reference for similar bridge projects crossing railways and highways.

参考文献

[1] 李韧.大吨位连续梁上跨既有铁路转体施工技术研究[J].建筑技术,2024,55(3):305-308.

[2] 蒋海涛.高速铁路桥梁跨既有营业铁路施工技术[J].铁道建筑,2020,60(11):48-52.

[3] 庄碧涛,李前名,李雅香.单线铁路2×72m曲线槽箱组合梁桥转体方案研究[J].铁道勘察,2025,51(2):136-142.

[4] 朱永兵.上跨铁路站场咽喉区连续钢箱梁设计与施工[J].城市道桥与防洪,2023(1):151-154,158.

[5] 赵凯兵.基于极不平衡条件下钢箱梁桥转体施工的研究[J].铁道建筑技术,2018(8):60-63.

[6] 刘明虎,孟凡超,李国亮,等.斜拉桥施工期取代临时墩的拉索平衡结构体系研究[J].桥梁建设,2020,50(1):26-31.

[7] 姚长见.上跨铁路钢箱梁桥转体施工挠度控制方法分析[J].铁道建筑,2017(4):26-29.

[8] 吴帅峰,张巨生.武汉市和平大道跨工人村车辆段主桥设计[J].桥梁建设,2025,55(6):137-144.

[9] 蔡建业.独塔斜拉桥超大吨位转体结构体系设计研究[J].铁道工程学报,2021,38(4):44-49.

[10] 李泽露,李新伟,李华鹏,等.基于云监测平台的跨铁路桥梁转体智能监测技术及应用[J].世界桥梁,2024,52(4):69-76.

[11] 王燎原.六景郁江特大桥钢混段钢箱梁吊装关键技术研究[J].铁道建筑技术,2024(3):105-107,144.

[12] 谭海雄,任虹昌,郭国和.黄茅海大桥临时墩设计与施工技术研究[J].公路,2025,70(5):148-153.

基本信息:

中图分类号:U445.4

引用信息:

[1]徐鹰.大纵坡长悬臂钢箱梁斜拉扣挂转体关键技术[J].铁道建筑().

基金信息:

中铁十一局集团A类科技创新项目(24-AⅡ-03)

发布时间:

2026-07-13

出版时间:

2026-07-13

网络发布时间:

2026-07-13

检 索 高级检索

引用

GB/T 7714-2015 格式引文
MLA格式引文
APA格式引文